Installing new pipeline with various diameter for the new palm oil manufacturing. Pipeline use to supply fresh water from the river to the factory and the employee houses. The project finished with satisfactory results.
Our Product Quality Standard
Quality Management system: ISO 9001:2015
Product standard: HDPE pipe SNI 4829.2:2015
Material standard: HDPE #1 Premium material applied
Note:
International hdpe welder certificate technician
Client : PT. Tirta Kimia
Location : Pelintung, Kawasan Industri Dumai
Area : –
Finished On : April 23, 2017
Value : $$$
Remarks : The project was completed under the budget, with the savings returned to the owner.
Description
New pipeline installation using our pipe installation services. Installation time is less than 2 (two) weeks with 3 (three) months retention. Pipe diameter is various start from 110 mm up to 200 mm.
The Challenges
A short deadline terms applied to this project with limited electricity to install the pipeline.
Project Goals
To flow the fresh water from nearest water springs to the palm factory and the employee residence.